Reorder point calculator

Add your products with what is in stock and how many you sell a day. The table tells you which to order now and how many. The lead time and safety days are typical. Change them to match your supplier.

Your supplier

Typical figures for a wholesale market in Lahore or Karachi. Change them to match your supplier.

days

From placing the order to the stock reaching you.

Typical
days

Days of sales kept as a cushion for late deliveries.

Typical
days

How many days of sales you buy in one go. Empty means 30.

Typical

Your products

Daily sales is the pieces you sell in an average day. Pieces sold in 30 days divided by 30 is a good start. A product with no daily sales is skipped.

Leave lead days empty to use the delivery time above. Enter a pack size if your supplier sells in sixes or dozens. Working out cloth for a batch? Try the fabric calculator.

For the printed sheet

Your numbers and these details stay on this phone or computer. They are saved here so the page opens as you left it.

What to do

—

Product Reorder at Order When

Enter daily sales for a product to see its row.

Stock sorted? Now sell it on your own store.

Storelala gives you an online store at yourbrand.storelala.com with cash on delivery built in. Lite is free forever, no card needed.

Start your store

Questions

What is a reorder point?

It is the stock level at which you place a new order. Your supplier needs some days to deliver, and you keep selling in the meantime. The reorder point is the pieces you sell during that wait, plus a cushion.

How is the reorder point worked out?

Daily sales multiplied by the lead time plus the safety days. If you sell 4 a day, the supplier takes 4 days and you keep 3 days of cushion, the reorder point is 4 × 7 = 28 pieces. When stock falls to 28 or below, order.

What is safety stock?

Extra stock that covers a late delivery or a busy week. The tool takes it in days of sales. Three days is a typical start. Raise it if your supplier is often late, for example around Eid, when markets close for days.

How much should I order?

The tool orders enough for the number of cover days you choose, based on daily sales. If your supplier sells in packs of 6 or 12, enter the pack size and the quantity is rounded up to a whole pack.

What does it mean when a product runs out before the order arrives?

Your stock is lower than what you will sell during the lead time. Even if you order today, you will be out for some days. The table marks these so you can call the supplier first or ask for a faster delivery.

How do I find my daily sales?

Take the pieces sold over the last 30 days and divide by 30. If sales jump in some weeks, use the busier figure for that product. Decimals such as 1.5 a day are fine.